5MW Geothermal Power Plant on Vanuatu
($37,000 advisory support for $14,700,000 total investment)
Purpose: Supporting the completion of a pre-exploration
feasibility analysis for a geothermal power plant investment on
Vanuatu.
Summary: A geothermal consultant was hired to advise the
equity investor and two development banks. Once completed, the 5
MW geothermal plant would provide 60% of the power to the island,
replacing diesel fuel as the principal source of energy. To further
facilitate the process, UNEP is also providing third party expertise
to the Vanuatu Ministry of Environment, Energy, Minerals and Water
Affairs to prepare for negotiations and the tendering process.
Place and duration: Vanuatu, 8 months
Status: IAF support completed 3Q2000. Under development.
|